WELD COUNTY – ROAD MAINTENANCE, CONSTRUCTION and RECLAMATION CLOSURES:
CR 25 from Hwy 392 to CR 70 6/5/2018 thru 6/29/2018 culvert replacement

CR 25 from CR 86 to CR 88 6/12/2018 thru 6/15/2018 cattle guard install

CR 35 from CR 38 to CR 40 6/4/2018 thru 6/29/2018 bridge re-deck

CR 49 from I- 76 Frontage Road 2/22/2018 on indefinitely flooding waters
South to CR 14.75
CR 70 from CR 41 to CR 43 6/5/2018 thru 6/8/2018 culvert replacement

DAY CLOSURE
CR 50 from CR 59 to CR 61 beginning June 7, 2018, and continuing thru June 8, 2018.

CR 61 from CR 50 to Hwy 34 beginning June 11, 2018, and continuing thru June 12, 2018.

CR 90 from CR 43 to CR 57 (Hwy 14) beginning June 5, 2018, and continuing thru July 5, 2018.

CR 47 Corridor – (Weld County Project) Contractor: Interstate Highway Construction
Segment 1: CR 47 from CR 60.5 to CR 64 will be closed starting 11/27/2017.
Segment 2: CR 47 from CR 64 to Hwy 392 will also be closed starting 1/3/2018.
Expected to re-open 7/9/2018.

CR 68 from Hwy 392 to CR 61 will be closed from 5/22/2018 thru 9/17/2018 for replacement of bridge.
Contact: Lawrence Construction Company – Don Hanneman 303-880-1940